Testing a whole house before a full remodel
Example project

- Home
- 1960s single-story stucco house in West Dublin, on a sloping lot with a dry garden
- Original request
- New kitchen and bathrooms, smooth ceilings and a sliding door cut into the back wall
- Testing
- About 14 samples from the ceilings, wall texture, flooring, ducts and stucco
- Found
- Asbestos in the living room and hall ceiling texture and in the kitchen sheet vinyl
- Clear
- No asbestos in the wall texture, ducts or stucco
- Timeline
- Report ready about a week after the visit
- Estimated survey cost
- $1,300
Scope of work
A visit to sample each material the remodel will touch, from the ceilings and walls to the floors, the ducts and the stucco around the new door, lab fees and a written report the owners can hand to every bidder. Removal of the two positive materials is priced separately.
Project overview
In this example, the owners of a 1960s house in West Dublin are planning a remodel of most of the house. For a house, the air district asks for a lab test of five kinds of material before they are disturbed: ducts, acoustic ceilings, textured walls, stucco and floors. The owners have them all tested in one visit.
Two materials come back positive, the ceiling texture and the kitchen sheet vinyl. Everything else is clear, so the new door goes through the stucco the usual way and only those two materials are removed under asbestos rules before the builder starts.
The goal
The goal is one report that tells the owners and their builder exactly which materials need asbestos removal and which do not.
Process
- Before the visit We go through the plans with the owners and list every material the work will touch.
- Visit Samples from each ceiling, wall finish, floor layer, the ducts and the stucco by the new door.
- Within a week Lab results and a written report listing what tested positive and what is clear.
- Then The report goes to every bidder, and the removal of the two positive materials is priced and booked.
Planning right
- We test first, so every builder prices the same work.
- The written report can go straight into the permit file.
- A positive ceiling over 100 sq ft needs a J# before it comes down. Allow 10 working days.
- Keep the report. It also helps with later projects and when the house is sold.