Example Asbestos Removal Projects in Dublin, California

Every project below starts with a sample, and each one shows the building, the lab result, what happens next, the time it takes and an approximate cost.

Testing a whole house before a full remodel

Example project

Single-story 1960s stucco house with a flat-roofed wing and a deep porch on a sloping lot with agaves and boulders
Home
1960s single-story stucco house in West Dublin, on a sloping lot with a dry garden
Original request
New kitchen and bathrooms, smooth ceilings and a sliding door cut into the back wall
Testing
About 14 samples from the ceilings, wall texture, flooring, ducts and stucco
Found
Asbestos in the living room and hall ceiling texture and in the kitchen sheet vinyl
Clear
No asbestos in the wall texture, ducts or stucco
Timeline
Report ready about a week after the visit
Estimated survey cost
$1,300

Scope of work

A visit to sample each material the remodel will touch, from the ceilings and walls to the floors, the ducts and the stucco around the new door, lab fees and a written report the owners can hand to every bidder. Removal of the two positive materials is priced separately.

Project overview

In this example, the owners of a 1960s house in West Dublin are planning a remodel of most of the house. For a house, the air district asks for a lab test of five kinds of material before they are disturbed: ducts, acoustic ceilings, textured walls, stucco and floors. The owners have them all tested in one visit.

Two materials come back positive, the ceiling texture and the kitchen sheet vinyl. Everything else is clear, so the new door goes through the stucco the usual way and only those two materials are removed under asbestos rules before the builder starts.

The goal

The goal is one report that tells the owners and their builder exactly which materials need asbestos removal and which do not.

Process

  1. Before the visit We go through the plans with the owners and list every material the work will touch.
  2. Visit Samples from each ceiling, wall finish, floor layer, the ducts and the stucco by the new door.
  3. Within a week Lab results and a written report listing what tested positive and what is clear.
  4. Then The report goes to every bidder, and the removal of the two positive materials is priced and booked.

Planning right

  • We test first, so every builder prices the same work.
  • The written report can go straight into the permit file.
  • A positive ceiling over 100 sq ft needs a J# before it comes down. Allow 10 working days.
  • Keep the report. It also helps with later projects and when the house is sold.

Get a free quoteMore about renovation and demolition abatement

Painted popcorn ceiling before recessed lights

Example project

Living room with a textured ceiling, walls and floor covered in plastic, a doorway sealed with plastic and a HEPA air unit
Home
1970s single-story house in Pleasanton
Original request
Six recessed lights in the living room ceiling
Testing
Sample taken through the paint, with asbestos in the texture
Room
About 230 sq ft of ceiling, one wide window
Work
Whole ceiling stripped wet inside plastic, with a HEPA air unit
Timeline
J# wait of 10 working days, then two to three days of work
Cost
$3,300

Scope of work

A lab test of the texture, the room emptied, walls and floor covered in plastic, a sealed doorway and a HEPA air unit, the painted texture soaked and scraped off, sealed bags, a HEPA vacuum and wet wipe, and disposal. Add the J# fee from the price table. The lights, a skim coat and paint are extra.

Project overview

In this example, the owners of a 1970s house in Pleasanton want recessed lights in the living room. The ceiling still has its sprayed texture, painted over at least once, so a sample goes to a lab before the electrician cuts any holes. It comes back positive.

Cutting six holes would still be asbestos work, done six times. The owners choose to remove the whole ceiling once. At 230 sq ft it needs a J#, and paint makes the texture slower to soak, so the job takes an extra day.

The goal

The goal is a ceiling the electrician can cut freely, stripped of its asbestos texture and ready for a skim coat.

Process

  1. First visit A sample of the texture, taken through the paint, goes to a lab.
  2. Before work J# filed; the work date is set 10 working days out.
  3. Day one Furniture out, plastic on walls and floor, HEPA unit running.
  4. Days two and three Texture soaked and scraped off, bagged and sealed, then the room is cleaned before the plastic comes down.

Planning right

  • Painted texture needs more soaking time. Tell us if it has been painted, even once.
  • The electrician can cut the light holes the day after the plastic comes down.
  • A skim coat over the bare drywall gives a smooth, modern ceiling.
  • Neighboring rooms with the same texture can be added now for less than a second visit later.

Get a free quoteMore about popcorn ceiling removal

Duct wrap removed before a furnace replacement

Example project

Crawl space with wood posts and beams and round ducts wrapped in torn white paper insulation, with brick walls behind
Home
1950s single-story house in Livermore, with the ducts in a deep crawl space
Original request
Replace the old furnace and connect it to the existing ducts
Testing
Lab test of the white paper wrap on the main duct found asbestos
Work
About 60 sq ft of wrap on the main duct and its joints next to the furnace
Timeline
Lab result in a few days, then one long day of removal before the installer comes
Cost
$2,800

Scope of work

A sample of the duct wrap, plastic on the crawl-space floor around the work area, the wrap and the joint tape kept wet and cut away from the main duct near the furnace, sealed bags, a HEPA vacuum of the area and disposal. The furnace and any new ducts are priced by the heating contractor.

Project overview

In this example, the owners of a 1950s house in Livermore are replacing an old furnace. The ducts run through a deep crawl space, and the main duct is wrapped in white paper insulation that is torn in places. The installer will cut into it to connect the new furnace.

The wrap tests positive. Before the installer arrives, the wrap and tape come off the length of duct nearest the furnace, about 60 sq ft of wrap, kept wet inside plastic. Duct wrap is counted by area, and 60 sq ft is under the 100 sq ft that needs a J#. The rest of the ducts are checked and left for a later job.

The goal

The goal is a new furnace connected to clean duct, with the damaged wrap near it gone and the crawl space left tidy.

Process

  1. First visit Sample of the duct wrap and a look at the whole crawl space.
  2. Before work The installer marks where the new furnace will connect.
  3. Removal day Plastic laid, wrap and tape wetted and cut away, waste bagged, the area vacuumed.
  4. Next day The installer connects the new furnace to bare metal duct.

Planning right

  • Call us when the furnace quote comes in, so the test is done before the installer is on site.
  • Torn wrap in a crawl space sheds fibers. Keep the access hatch closed until it is dealt with.
  • The rest of the old wrap can come off later as its own job, or all at once if the ducts are replaced.
  • New duct joints are sealed with foil tape, not cloth tape.

Get a free quoteMore about HVAC duct and insulation removal

Kitchen sheet vinyl taken up before a house goes on the market

Example project

Older kitchen with white cabinets and a gas stove, patterned sheet vinyl lifted at one corner to show its gray backing, and plastic over the counters
Home
1940s single-story house in Livermore
Original request
Sell the house with the worn kitchen floor gone and a clean report
Testing
Sheet vinyl, its felt backing and the black adhesive under it sampled one by one
Found
Asbestos in the black adhesive only; the vinyl and the felt are clear
Area
Kitchen, about 220 sq ft, cabinets and stove staying
Work
Clear vinyl lifted, then the adhesive scraped off wet inside plastic, around the cabinets
Timeline
Two days of removal before the listing photos
Cost
$4,400

Scope of work

A lab test of the floor, the kitchen sealed with plastic and the counters covered, the sheet vinyl cut into strips and lifted wet up to the cabinet bases, the black adhesive under the felt scraped off the subfloor wet, sealed bags, a HEPA vacuum and wet wipe, and disposal. A new floor is extra.

Project overview

In this example, the sellers of a 1940s house in Livermore find the kitchen sheet vinyl curling at the corner by the sink, with gray felt showing underneath. Rather than leave buyers to guess, they have each layer tested before listing. The vinyl and its felt are clear, but the black adhesive that holds them down is positive.

The adhesive is the asbestos layer, so once the clear vinyl is lifted it is scraped off wet inside sealed plastic, strip by strip up to the cabinet bases, which stay. Scraped wet by hand and never sanded, the adhesive stays nonfriable, so no J# is needed, and the sellers hand buyers the lab report and the waste records with the disclosures.

The goal

The goal is a clean kitchen subfloor and a clear paper trail before the house is listed.

Process

  1. First visit Samples of the vinyl, the felt and the adhesive go to a lab; the curled corner is taped down.
  2. Before work Counters, stove and cabinets covered; plastic up.
  3. Day one Kitchen sealed, vinyl cut into strips and lifted wet.
  4. Day two Adhesive scraped wet, waste bagged, the room cleaned and checked.

Planning right

  • Each layer of an old floor can test differently, down to the glue.
  • A lab report and waste records answer buyer questions better than a guess.
  • Cabinets that stay are wrapped, and the vinyl under them is left in place.
  • Pets and children stay out of the kitchen until the plastic comes down.

Get a free quoteMore about floor tile and sheet vinyl removal

Textured wall cut open around an electrical panel for a larger panel

Example project

Room wall with a rectangle of drywall cut away around a gray electrical panel, plastic taped around the opening and over the wood floor
Home
1960s single-story house in Dublin
Original request
A larger electrical panel in the same spot, with new wiring run through the attic
Testing
Separate lab tests of the thin wall texture and the joint compound
Found
Asbestos in the wall texture; none in the joint compound
Opening
About 3 by 6 ft around the panel, the only opening the electrician needs
Work
One opening cut out wet inside taped plastic, with a filtered air unit
Timeline
One day, ahead of the electrician
Cost
$1,900

Scope of work

Separate samples of the texture and the joint compound, plastic taped around the panel wall and over the floor with a filtered air unit, the textured drywall cut out wet around the panel, sealed bags, a HEPA clean and disposal. The new panel, patching and paint are extra.

Project overview

In this example, a 1960s house in Dublin is getting a larger electrical panel in the same place. The new wires run through the attic, so the only wall that has to open is the one around the panel. The lab finds asbestos in the thin texture on the wall, not in the joint compound.

One rectangle about 3 by 6 ft is cut out wet inside taped plastic, well under 100 sq ft, so no J# is needed. The electrician swaps the panel the next day.

The goal

The goal is one clean opening for the new panel, with no asbestos dust in the rest of the house.

Process

  1. First visit Samples of the texture and the joint compound; the opening is marked with the electrician.
  2. Removal day Plastic taped around the wall, the opening cut out wet and bagged, the area cleaned.
  3. Next day The electrician swaps the panel.
  4. Then The drywall contractor patches the opening.

Planning right

  • Running new wire through the attic can save opening more walls.
  • Plan the power shutdown with the electrician, since the opening comes first.
  • Drilling or sawing a positive texture makes dust. Leave it to the enclosure.
  • File the report with the house papers for the next electrical job.

Get a free quoteMore about wall texture and drywall removal

Floor tile and wall compound out of an office suite

Example project

Empty office suite with vinyl tile floor, a drop ceiling, tall windows and a plastic zipper door with a blue air filter unit
Building
Office suite in a 1970s two-story office building in Dublin, other tenants still open
Original request
Turn the suite into a small medical clinic
Testing
Certified survey of the suite
Found
Asbestos in the floor tile and adhesive and in the joint compound of two walls coming out
Area
About 1,200 sq ft of floor and 250 sq ft of wall
Work
Evenings and weekends, behind a zipper door with filtered air
Timeline
Survey and J#, then about two weeks of after-hours work
Cost
$16,000

Scope of work

A certified survey of the suite, a J#, a sealed work area with a zipper door to the hallway and a filtered air unit, the floor tile and adhesive removed wet, the two walls taken down, sealed and labeled waste with shipment records, and a clearance air test. The air district fee and the clinic build-out are extra.

Project overview

In this example, a 1970s office suite in Dublin is being turned into a small clinic. The building is commercial, so a certified consultant surveys the whole suite before any work. The floor tile, its adhesive and the joint compound on two walls coming out test positive.

The other tenants stay open, so the work runs on evenings and weekends behind a zipper door, with filtered air pulling from the suite. A clearance air test is done before the builder moves in.

The goal

The goal is an empty suite with the floor tile and wall compound gone, ready for the clinic build-out, with the other tenants open throughout.

Process

  1. Weeks one and two Certified survey of the suite and lab results; J# filed.
  2. Before work Work hours agreed with the building manager; tenants told the dates.
  3. Evenings and weekends Suite sealed, floor tile and adhesive lifted wet, the two walls taken down and bagged.
  4. Last night Clean, inspection and a clearance air test before the plastic comes down.

Planning right

  • An earlier survey of the building, if the landlord has one, can save sampling.
  • Owners of commercial buildings from before 1979 have to tell the people inside about known asbestos.
  • Freight elevators and loading doors may have set hours. Waste removal is planned around them.
  • The clearance air test result is part of the file the clinic will keep.

Get a free quoteMore about commercial asbestos abatement

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (925) 709-5697

Call (925) 709-5697